Clients arranging an Electrical Installation Condition Report often receive very different descriptions of what will be tested, how much of the installation will be sampled, who will attend and what the finished report will contain. This guide explains what to expect and the checks worth making before appointing any contractor.
Download the branded EICR client guide (PDF)
What is an EICR?
An Electrical Installation Condition Report is a professional assessment of an existing fixed electrical installation. It combines inspection and testing to determine, so far as reasonably practicable, whether the installation is satisfactory for continued service.
The fixed installation includes wiring, consumer units, protective devices, switches, socket-outlets, lighting points and permanently connected equipment within the agreed scope. The inspection considers matters such as electric-shock protection, fire and heat risks, earthing and bonding, deterioration, damage and suitability for continued use.
An EICR is a report, not a warranty that every concealed part of an installation is defect-free. The extent and any limitations must be stated clearly.
What happens during an EICR?
- Scope: the property, reason for the report, accessible areas and known operational limitations are agreed.
- Inspection: accessible fixed equipment, consumer units, earthing, bonding, protective devices, wiring systems and accessories are assessed.
- Testing: appropriate electrical tests are carried out. Temporary isolation and loss of power will normally be required.
- Reporting: the client receives the EICR whether the outcome is satisfactory or unsatisfactory.
Are only 20% of the circuits tested?
There is no universal rule that only 20% of circuits are tested.
Every identified circuit should be accounted for on the report and assessed using suitable inspection and test evidence. In a typical rented home, current authoritative guidance expects the incoming supply, main earthing and bonding, every consumer unit, all RCDs and relevant points on every final circuit to be covered.
Sampling normally relates to the internal dismantling of accessories and connections. It should be representative and risk-based, recorded on the report and increased where defects or concerns are found. A representative number of points should be opened on every final circuit, subject to access and the agreed limitations.
Normal limitations
- An EICR is normally non-destructive. Concealed cables, inaccessible voids and equipment requiring damage to the building fabric are not normally inspected.
- Portable appliances are not part of the fixed-installation EICR.
- Fire-alarm, emergency-lighting and specialist-system performance tests are separate unless expressly included.
- Distributor and supplier equipment is normally subject to visual inspection only.
Understanding C1, C2, C3 and FI codes
- C1 – danger present: immediate action is necessary to remove the risk of injury. The report is unsatisfactory.
- C2 – potentially dangerous: urgent remedial action is necessary. The report is unsatisfactory.
- C3 – improvement recommended: the matter is not classified as dangerous or potentially dangerous. A satisfactory result is possible.
- FI – further investigation: further investigation is advised because a possible issue could not be fully classified within the agreed extent and limitations. Under BS 7671:2018+A4:2026, FI is advisory and does not by itself make the report unsatisfactory.
Important landlord note: at the time of writing (November 2026), the English rented-sector regulations require further investigative work to be completed within 28 days. Amending regulations approved by Parliament in October 2026 are due to come into force on 30 November 2026. For inspections completed on or after that date, the 28-day legal duty covers remedial work only, not FI items. Reports from earlier inspections stay under the old rule. Landlords should still act promptly on FI observations.
For more detail, see our article explaining how Amendment 4 treats the FI classification.
Who is qualified to carry out an EICR?
English rented-sector legislation requires a qualified person – meaning somebody competent to undertake the inspection and testing. The legislation does not prescribe one particular qualification title.
From 1 October 2026, revised Electrotechnical Assessment Specification requirements apply to certified electrical businesses. Relevant employed persons and Qualified Supervisors independently undertaking or responsible for periodic inspection and testing require an accepted qualification, evidence of at least two years’ relevant experience and continuing professional development.
Compliance is checked through certification-scheme assessments and action plans may be agreed where evidence is incomplete. The EAS deadline for individual competence was 1 October 2026. City & Guilds 2391 is an accepted route, but the law does not require that exact qualification title in every case. A trainee may assist only within appropriate close supervision and should not be presented as independently carrying out or taking responsibility for the EICR.
What should the completed report contain?
An Inspect Electrical EICR includes:
- The complete EICR with the overall satisfactory or unsatisfactory assessment.
- The schedule of inspection and circuit details and test results.
- Plain-English observations and classification codes.
- The stated extent, limitations and recommended next-inspection date.
- A photographic record of key accessible equipment and relevant observations.
Photographs support the written findings and test schedules. They do not replace electrical test evidence or extend the inspection into inaccessible areas.
What should clients check before appointing a contractor?
Ask every contractor the same questions in writing:
- Who will carry out and sign the EICR?
- What qualifications, inspection experience and continuing professional development does that person have?
- Can the contractor’s registration and insurance be independently verified?
- Which consumer units, circuits, buildings and fixed equipment are included?
- How will sampling and any limitations be recorded?
- What access, isolation and loss of power will be required?
- What exactly is included or excluded from the quotation?
- How will observations be coded and explained?
- Will the complete report be supplied whether the result is satisfactory or unsatisfactory?
- Are photographs included, and when will the report be delivered?
A credible quotation should be specific to the property and agreed scope. There is no reliable universal duration, fixed percentage of circuits or standard price that applies to every installation.
Inspect Electrical’s qualifications and reporting
We confirm who will attend. Alan holds City & Guilds 2391, with City & Guilds 2400 as an additional qualification. Lucy holds the City & Guilds 2391-52 Level 3 Award in Initial and Periodic Inspection and Testing of Electrical Installations.
Inspect Electrical Ltd is an NICEIC Approved Contractor (registration 502674), with public liability insurance through Allianz. Scope, access, likely site time and the quotation are property-specific. Coding follows the current edition of BS 7671 and Electrical Safety First guidance, supported by engineering judgement.
We undertake homeowner EICRs and commercial EICR and fixed-wire testing, with clear reporting and photographic documentation.
Authoritative sources
- IET – BS 7671 Amendment 4 transition
- Electrical Safety First – Best Practice Guides
- NICEIC – EAS changes
- EAS – October 2026 requirements and transition FAQs
- GOV.UK – electrical safety standards in rented homes
This article provides general information and is not legal advice. Duties depend on the property, tenure, report date and circumstances. The signed EICR and applicable legislation take precedence.
Need an electrician in Bromley, Chislehurst or SE London?
NICEIC Approved · 30+ years’ experience · Free written quotes